Project Scope
Complete site remediation and cleanup of a major fire that destroyed
approximately 50,000 square feet of manufacturing space. Shipped off site for disposal 750
cubic yards of lead-contaminated debris, 450 cubic yards of oil-contaminated debris and
150 drums of caustic chemicals and PCB Large Capacitors destroyed by the fire.
click the pictures for
larger view
Phase I

BG Environmental, Inc.'s site trailer.

Phase I of burned out manufacturing company clean-up. Approx. 50,000
sq. ft. of floor space was destroyed by fire. Phase I was approx. 20,000 sq. ft.

Phase I at 50% completion - ahead of schedule and under budget.

Phase I oil contaminated material in roll off
containers.

Phase I at 100% completion. Waste material in drums waiting for analytical
results. Phase I was completed on time and under budget.

Phase I required the removal and disposal of 450 cubic yards of oil contaminated
debris and soil.